Transformer kVA from load

Transformer kVA needed for an active load at a given power factor, with an optional design margin.

Method

Load-basis kVA calculation with an optional explicit design margin.

Equations

Sb = PPF
Sd = Sb · (1 + m100)

Symbols and units

SymbolQuantityUnit
Inputs
PActive load (after diversity)kW
PFPower factor0–1
mDesign margin (blank = 0)%
Results
SbBase required kVAkVA
SdDesign required kVAkVA

All symbols and units in the library

Assumptions and limits

  • No standard rating, derating, redundancy or growth assumption is applied.

In practice

  • Select the next standard rating at or above Sd, then check loading, ambient derating and redundancy for the project.

Worked example

The input values are the calculator's own verification test, run through the calculator. They show the working; they are not design values.

Inputs

PActive load (after diversity)800 kW
PFPower factor0.8 0–1
mDesign margin (blank = 0)20 %

Results

SbBase required kVA1,000 kVA
SdDesign required kVA1,200 kVA

A preliminary check for engineer review, not an engineering approval. The project calculation to the applicable codes, authority requirements and specification governs.