Hot water demand: daily and peak hour

Daily and peak-hour hot-water demand totals from a schedule of usage rows (apartments, rooms, beds, fixtures and so on).

Method

Daily and peak-hour hot-water demand aggregation over explicit usage rows.

Equations

Vday = Σ(n · qd)
Vph = Σ(n · qd · fph)

Symbols and units

SymbolQuantityUnit
Usage rows: one row each
nQuantity of unitsno.
qdDaily hot water per unitL/unit/day
fphPeak-hour factor–
Results
VdayTotal daily hot waterL
VphTotal peak-hour hot waterL

All symbols and units in the library

Assumptions and limits

  • Usage rates and peak factors are explicit row inputs; no defaults.

In practice

  • Usage per unit and the peak-hour factor are project inputs; take them from the plumbing code or design guide your project follows.

Worked example

The input values are the calculator's own verification test, run through the calculator. They show the working; they are not design values.

Inputs

Usage rows

n (no.)qd (L/unit/day)fph
2500.5

Results

VdayTotal daily hot water100 L
VphTotal peak-hour hot water50 L

A preliminary check for engineer review, not an engineering approval. The project calculation to the applicable codes, authority requirements and specification governs.